To Shut Down:

thumb

1. Switch off the AC in the switch box with the breakers the switch marked “Solar PV Main Switch”

thumb

2. Switch off the DC isolation breaker. Usually a separate small box next to the inverter.
(There are 2 in this pic switch them both off.)

thumb

3. Wait for 3 minutes

To Reboot:

thumb

4. Switch on the DC breaker.

thumb

5. Switch on the AC breaker.

thumb

6. The start up process normally
takes around 120 seconds

At this stage the inverter should be running and feeding the house and excess should be going to the grid.